Development Management Model
Budget managed construction spend, fee accrual, retention, payroll and working capital.
Estimate hard construction cost from gross area, unit cost and contingency.
Calculated directly from the assumptions shown.
Move from this screening result to the complete Development Management Model.
Buy now · €49Construction cost = gross area × cost per square metre × (1 + contingency).
8,000 sqm at €2,200 per sqm plus 7.5% contingency gives €17,600,000 base cost and €1,320,000 contingency: €18,920,000 in total.
Use this for early screening. Add professional fees, enabling works, tax, finance, FF&E and land separately.
Estimate hard construction cost from gross area, unit cost and contingency.
Construction cost = gross area × cost per square metre × (1 + contingency).
Use it as a transparent screening calculation. Validate deal-specific tax, timing, financing and legal assumptions in a complete underwriting model before making a decision.
No. The calculator is free and runs in your browser. FormulaPlanet does not store your projects, inputs or results.
No calculation is public by default. A shareable link is only created when you explicitly choose to copy one; that link contains the assumptions shown in its URL.
Differences usually come from timing, compounding, sign conventions, fees or a different definition of the numerator or denominator. Match every period and definition before comparing.
Use this for early screening. Add professional fees, enabling works, tax, finance, FF&E and land separately.
Mixing gross and net area; Applying cost per square foot to square metres; Omitting abnormal works; Treating contingency as a substitute for scope.